RoRo Conversion and Survey

Slideshow

RoRo Conversion and Survey 2

RoRo Conversion and Survey 1

 

 

 

Condition Survey on RoRo Vessel and installation of stiffening and container dove tails to accept larger sized container cargo.

Vessel was brought into port to carry out the conversions; expectation was to complete the work in two phases with the lower main deck being completed on first port call after charter starting. Vessel sailed on time with all stiffeners installed and dove tails hold downs installed, no requirement to complete on first port call since the full scope of work was done by sailing time. Vessel sailed on time with no charter loss.

At same time on hire survey and vessel condition survey was carried out and complete with the client receiving the report and photos before the vessel sailed.

Vessel docked, thrusters stripped and rebuilt, windlass stripped and rebuilt, sea valves serviced and inspected, hull cleaned and coated, Stern seals replaced and steering gear over hauled.  Special survey carried out and vessel sailed on time on budget with no Class, Flag or Client Issues hanging over the vessel.

Gallery

Comments are closed.